–°onstruction progress
Photo reports from the construction site
Construction Report 12.07.2019

1-2 sections of the residential complex

  • All monolithic works from the 1st to the 10th floor were completed
  • The foundation is set for the stylobate part of the house
5-6 sections of the residential complex
  • start of foundation laying works (195 piles out of 560 laid)

Construction Report 13.01.2019

Video review of the construction of LCD "DERBY STYLE HOUSE"

WINTER PHOTO REPORT FROM THE CONSTRUCTION SITE

Report from the construction site of the residential complex

Construction Report 12.12.18

Aero-flying construction site 12.12.18