Construction report 12.07.2019

1-2 sections of the residential complex

  • All monolithic works from the 1st to the 10th floor have been completed.
  • The foundation for the stylobate part of the house is being established

5-6 sections of the residential complex

  • start of foundation laying works (195 piles out of 560 laid)